Enter your structural elements (footings, ground beams, columns, beams, slabs, walls, hollow-block floors) with their number, length, width and height: the tool computes the concrete, the formwork, the steel, the blinding concrete, the excavation and the backfill, then the bill of quantities in Excel.
2. Assumptions (excavation, blinding concrete, floors)
Take-off
The calculation rules
- Concrete = number × length × width × height of the element. Hollow-block floor: area × concrete volume per m² (0.08 m³/m² for a 16 + 4 floor, adjustable).
- Formwork: vertical faces of footings, ground beams and walls; four faces of columns; both sides and the soffit of beams; underside of slabs.
- Steel: concrete × ratio in kg/m³ specific to each element (60 for a footing, 120 for a column…). If your bar schedule gives the real weight, put the exact ratio on the row.
- Blinding concrete under footings and ground beams, with a projection; excavation for footings with a working space; backfill = excavation − buried concrete.
Entering a project in ten minutes
Start from the formwork drawing: one row per footing type (F1, F2…) with their number, one row per line of ground beams (or the total length), one row per level of columns, beams and floors. The detail per element lets you trace every quantity in the bill of quantities.
Frequently asked questions
How do I calculate the formwork of a beam?
Length × (2 × depth + width): both sides and the soffit. For a beam cast into a slab, count only the downstand below the slab as the depth.
Which steel ratio should I use for a take-off?
Common orders of magnitude: footings 40 to 70 kg/m³, ground beams 70 to 100, columns 100 to 150, beams 90 to 130, slabs 70 to 100, walls 50 to 80. They depend on the loads and the seismic zone.
How many hollow blocks per m²?
About 8 blocks of 20 × 25 × 53 cm per m² with joists at 60 cm centres. The number can be adjusted to your manufacturer.
Is blinding concrete counted under ground beams?
Yes, with the same projection as under footings; a ground beam laid on hardcore or on fill can be entered without blinding by setting its thickness to zero.