Cut and fill volume online: earthwork between two surfaces
Paste the points of the existing ground and those of the design (or simply give a platform level): the tool triangulates both surfaces, computes cut and fill cell by cell, draws the difference map and prepares the bill of quantities in Excel.
Cut and fill
Cut and fill map
How the tool computes the volumes
Each set of points is first triangulated (Delaunay triangulation, as in Civil 3D or other survey software); the long edge triangles, which would invent ground beyond the survey, are discarded. A regular grid then covers the design: at the centre of each cell, the ground level and the design level are interpolated in their triangle. The difference gives a cut (ground higher than the design) or a fill (ground lower), multiplied by the cell area.
The cell size is chosen automatically from the size of the area (about 90,000 cells); you can force it. To check a result, halve the cell size: the volume should hardly change.
Two ways to describe the design
- Design points: the points of the platform, formation level and slopes, exported from your design software.
- Platform: a single level (earthworks for a plot, a building, a pond) or a level with slopes in X and Y.
Accepted files
Text pasted from Excel (name, X, Y, Z or X, Y, Z), TXT, CSV and XYZ files, and DXF: points, vertices of 3D polylines and 3D faces, 3D lines. Both surfaces must be in the same coordinate system (UTM, national grid…).
Frequently asked questions
Which earthwork method should I use: cross-sections or grid?
Cross-sections suit linear works (roads, canals); the grid method between two surfaces suits platforms, housing estates, ponds and slopes of any shape. This page uses the grid method; for a road, see the road take-off.
What accuracy can I expect?
The calculation is exact for the triangulated surfaces; the error mostly comes from the density of the survey. With a fine cell (0.5 to 1 m), the difference from survey software is generally below 1%.
My two surfaces do not overlap: why?
The ground and design points are in two different systems (for example a national grid and local coordinates), or X and Y are swapped. Choose the column order, or convert one file with the coordinate converter.
How many points can be loaded?
Several tens of thousands of points per surface: the triangulation runs in the browser in a few seconds.
Does the calculation include topsoil stripping?
No: it compares two surfaces. For topsoil stripping, add an item to the bill of quantities or lower the existing ground by its thickness.