Cut and fill calculation from survey points: the grid method

How much earth must be removed, and how much brought in, to build a platform? With a ground survey and a design level, the grid method answers in minutes. Here is how it works, with an example you can check by hand.

The method

  1. Model the existing ground. The survey points (X, Y, Z) are triangulated into a surface (TIN), so the ground level can be read anywhere.
  2. Model the design. Either other points (formation level, slopes) or a single platform level, horizontal or sloping.
  3. Lay a grid over the area. At the centre of each cell, read the ground level and the design level.
  4. Difference = ground − design. Positive: cut. Negative: fill. Multiply by the cell area.
  5. Add up cut and fill separately, then apply the bulking and compaction factors.

Worked example

A 20 × 20 m platform at level 100.00, split into four 10 × 10 m cells (100 m² each). Ground level at the centre of each cell: 100.60, 100.20, 99.80 and 99.50.

CellGroundDifferenceCut (m³)Fill (m³)
1100.60+0.6060
2100.20+0.2020
399.80−0.2020
499.50−0.5050
Total8070

The balance is +10 m³ in place. But cut swells once excavated: with a bulking factor of 1.25, the 80 m³ become 100 m³ of loose material to move. Four cells are only for the example; a real survey uses thousands of small cells.

Do it with your own survey

The cut and fill calculator takes your points pasted from Excel or a DXF, triangulates both surfaces, computes cut and fill cell by cell, draws the difference map and exports the bill of quantities to Excel. For roads, use the road earthwork take-off, which works from cross-sections.

Frequently asked questions

What cell size should I use?

Small enough to follow the ground: 0.5 to 2 m on most sites. To check, halve the cell size: the volumes should hardly change.

What is the difference between the grid method and cross-sections?

Cross-sections suit long linear works such as roads and canals. The grid method suits platforms, plots and ponds of any shape.

Which bulking factor should I use?

Often 1.20 to 1.30 for ordinary soil, more for rock. Your geotechnical study gives the value for your site.

Open the cut and fill calculator