Retaining wall and boundary wall take-off
Describe your retaining walls (reinforced concrete or rubble stone masonry, with a footing) and your boundary walls (concrete blocks or bricks, reinforced concrete posts): the tool computes the concrete, the masonry, the formwork, the steel, the excavation, the weep holes, the drain, the number of blocks, the mortar and the render.
3. Assumptions (excavation, posts, tie beams, masonry)
Take-off
Retaining walls
For each wall: length, height above the footing, thickness at the top and at the base (a battered wall is thicker at the bottom), width and thickness of the footing. The tool computes the concrete of the stem (trapezoidal section) and of the footing, or the volume of rubble stone masonry and its foundation concrete, the formwork of both faces, the steel by ratio, the blinding concrete, the excavation, the backfill, the weep holes (one every 2 m, two rows above 2.50 m in height) and the drainage fill behind the wall.
Boundary walls
A blockwork boundary wall is computed from its length and height: reinforced concrete posts at the chosen spacing (plus one at the end), foundation pads, ground beam under the wall, top tie beam, masonry area between posts, number of blocks (12.5 per m² for 40 × 20, wastage included), bedding mortar and render on one or two faces.
Frequently asked questions
How do I calculate the concrete volume of a battered wall?
Length × height × (top thickness + base thickness) / 2, plus the footing: length × width × thickness.
How many blocks for 1 m² of wall?
About 12 blocks of 40 × 20 cm per m² with 1 cm joints; 12.5 is often counted on site to allow for cuts. For other sizes, use the materials calculator.
Does a retaining wall need weep holes?
Yes, to drain the water that builds up behind the wall: generally a 100 mm PVC pipe every 2 m, combined with gravel drainage fill.
What spacing for the posts of a boundary wall?
Most often 3 to 4 m, with 20 × 20 cm posts fixed into pads or a ground beam.