Sewer and stormwater take-off online
Import the DXF of the longitudinal profile or paste manholes, distances, ground levels and invert levels: for each manhole the tool computes the trench, the bedding, the pipe volume, the initial and final backfill, the excavation for the manholes, counts blind manholes, connection chambers and gullies, then prepares the progress measurement and the bill of quantities in Excel.
4. Additional items (optional)
Take-off
The progress measurement method
This is how most sewer works are measured month by month, and it is the method of the tool:
- Manhole depth = ground level − invert level.
- Trench depth between two manholes = average of their depths + an over-excavation below the invert (0.20 m: bedding and pipe wall thickness).
- Trench length = distance between centres − outside width of a manhole (1.40 m): the manholes are excavated separately.
- Width = Ø + 0.60 m rounded to 0.10 (0.90 m for Ø 315, 1.00 m for Ø 400), editable.
- Bedding = length × width × 0.10; pipe volume = π Ø² / 4 × length.
- Initial backfill (sieved soil) up to 0.30 m above the pipe crown, less the pipe; final backfill (screened soil) up to the surface layer.
- Excavation for a manhole = (depth + over-excavation) × 1.40 × 1.40; the total earthworks add trenches and manholes.
An Excel file ready for the progress measurement
The file opens on the detail per manhole: one row per manhole, one row per section, with the formulas and the parameters at the top of the sheet. Then come the progress measurement (contract quantity, previous measurements, this month and cumulative) and the bill of quantities. Change the over-excavation or the width of a manhole: everything is recalculated.
Stormwater
The “Stormwater” mode uses the same method with reinforced concrete pipes and adds the gullies counted manhole by manhole. Channels and headwalls are entered as additional items.
Frequently asked questions
How do I calculate the earthworks of a sewer network?
Trenches between manholes (length between walls × width × average depth with the over-excavation) plus the excavation for each manhole ((depth + over-excavation) × outside side²).
What is the difference between initial and final backfill?
The initial backfill surrounds the pipe with sieved soil up to 20 to 30 cm above it, compacted by hand; the final backfill fills the rest of the trench with screened soil, compacted in layers.
How do I take off a drop manhole?
Enter two rows with the same manhole name and the same cumulative distance: the first with the incoming invert level (the higher one), the second with the outgoing level. The tool counts a single manhole, measured down to the lower invert; the upstream trench takes the incoming level, the downstream trench the outgoing level, and the bill of quantities adds an extra-over item for a drop manhole. In a DXF, two invert levels under the same manhole are read in the same way.
How do I enter blind manholes and connection chambers?
In the “Blind manholes” and “Conn. chambers” columns of the row of the upstream manhole of the section; the lengths of Ø 200 connections go in the “Conn. Ø 200” column.
Can I import a sewer longitudinal profile from Covadis?
Yes: the profile table (ground levels, invert levels, distances, manhole numbers) is read from the DXF; each node becomes a manhole.
Can the quantities of the progress measurement be edited?
Yes: in the Excel file, the contract quantities and those of previous months are in blue; the cumulative quantity and the percentage of the contract are recalculated.